(65)67322090

enquiry@tytolaw.com

The SIAC Streamlined Procedure: a faster route to resolving final account disputes up to S$1 million

Most contractors know about SOPA adjudication for recovering unpaid progress claims. Fewer know about the SIAC Streamlined Procedure — a new fast-track arbitration process introduced in 2025 that can produce a final, binding and enforceable award in under three months for construction disputes up to S$1 million. For final account disputes where SOPA is unavailable or time-barred, it is worth understanding.

Tan Joo Seng

Founder & Director. Tyto LLC

Legal basis
 
SIAC Rules 2025 (7th Edition), Rule 13 and Schedule 2 — Streamlined Procedure
 
In force from 1 January 2025. Applies to all arbitrations commenced on or after that date under the SIAC Rules, unless the parties agree otherwise (Rule 1.5).

STREAMLINED PROCEDURE AT A GLANCE

DISPUTE VALUE 

Up to S$1 million

Applies automatically unless excluded 

AWARD TIMELINE

3 months

From constitution of Tribunal

TRIBUNAL 

Sole arbitrator

Jointly nominated within 3 days; SIAC appoints if not agreed

FEES

Capped at 50%

Of SIAC’s standard Schedule of Fees maximum

DEFAULT PROCEDURE

Written submissions only

No hearing, no document production, no witness evidence

AWARD

Final & binding

Enforceable in Singapore and 170+ countries

What is a payment claim?

A payment claim is a formal document served by the claimant (the party who has done the work or supplied the goods) on the respondent (the party who owes payment). It sets out the amount claimed and the work or goods it relates to.

Under SOPA, a payment claim must be in writing and must be served in accordance with the contract. It should identify the contract and describe the work done or goods supplied during the relevant period. There is no prescribed form — but the document must comply with SOPA’s requirements to trigger the statutory regime.

Practical tip: Always mark your payment claims clearly as being made under the Building and Construction Industry Security of Payment Act. While this is not strictly required, it removes any ambiguity about whether the statutory regime applies.

What happens after a payment claim is served?

Once a payment claim is served, the respondent has 14 days to serve a payment response if the contract is silent on the period to provide a payment response, or such period as specified in the contract (subject to a maximum of 21 days). The payment response must either accept the claimed amount or set out the amount the respondent proposes to pay and the reasons for any difference.

If the respondent fails to serve a payment response, or serves one that does not pay the full amount claimed, the claimant may lodge an adjudication application.

Practical tip: Always mark your payment claims clearly as being made under the Building and Construction Industry Security of Payment Act. While this is not strictly required, it removes any ambiguity about whether the statutory regime applies.

The adjudication process - step by step

Payment claim served.

The claimant serves the payment claim on the respondent under the contract.

Payment response deadine.

The respondent serves a payment response within the period stated in the contract or within 14 days if no period is stated in the contract.

Dispute Settlement Period.

A seven-day period starting after the payment response period ends. The respondent may amend a payment response or serve a payment response in this period.

Adjudication window opens.

The day after the Dispute Settlement Period end, the claimant may lodge an adjudication application. This window is open for 7 days only.

Adjudication application lodged.

The claimant lodges the adjudication application with a Singapore Mediation Centre (SMC) authorised nominating body.

Adjudicator appointed.

The nominating body appoints an adjudicator within 7 days of the application being lodged.

Adjudication response.

The respondent may lodge an adjudication response within 7 days from the date when the adjudication application is served on it.

Determination issued.

The adjudicator issues a determination within 14 days (or a longer time if agreed by the parties) after the period when the respondent may lodge an adjudication response. 

Payment.

The respondent must pay the adjudicated amount if any within the time it is ordered to do so in the determination.

What if the respondent doesn't pay after a determination?

If the respondent fails to pay the adjudicated amount within the required period, the claimant may apply to the Singapore Courts to enforce the determination as if it were a court judgment. The Courts will generally enforce a determination unless the respondent can show a valid ground to set it aside — and these grounds are narrow.

Important warning: SOPA deadlines are strictly enforced. If you miss the 7-day window to lodge your adjudication application, you  lose the right to adjudicate that payment claim. The window cannot be extended. If you are approaching this deadline, contact us immediately.

Common questions

Can SOPA be used for claims for retention sums?

Yes, provided that the conditions for the release of the retention sum under the construction contract have been satisfied.

Does SOPA apply if the construction contract does not have any payment claim or certifiation mechanism?

Yes.  In such cases, the statutory deadlines in the Act will apply.

Does SOPA apply to supply contracts?

Yes. but with important differences. The respondent can provide its objection at any time before the date for payment. There is no dispute settlement period. Always verify which regime applies to your contract.

ABOUT THE AUTHOR

Tan Joo Seng

Founder & Director, Tyto LLC · SMC Senior Adjudicator · SIAC Panel Arbitrator

IN THIS GUIDE 

01

What is SOPA and who does it protect? 

03

The adjudication process – step by step.

02

What is a payment claim? 

04

What if the respondent doesn’t pay?

05

Common questions

Have a specific question about this topic ?

Book a free 30-minute consultation — we’ll give you plain advice with no obligation.